In the course of processing, AWK GmbH implemented the measure as a subcontractor in the new familiar structure.
A total of 90 articulated lorries were needed to transport the materials. This ensured a continuous supply of the necessary components to the construction site and contributed to the timely completion of the project.
A total assembly team of 6 people was deployed. Daniel Eberz was responsible for site management, while Marcel Lang was in charge of the crew.
Thanks to the excellent cooperation of all those involved, the project was completed without incident and within the specified time frame.
Client:
ARGE B33n Tunnel Röhrenberg Straßenbau (Storz + Schleith)
Products:
NoiseGard Professional | Height: 6 metres
Construction time:
Start of installation: week 23 on 4 June 2024
Completion: week 26 on 27 June 2024
Service life: approx. 4 years